Riana Dutamas Logo

Site Progress
SAVIO

Quarterly Progress Update



  • Sep 21

    Block: A&B - Stage: Completion

  • Sep 21

    Security Guard House - Stage: Completion

  • Sep 21

    Open Lawn - Stage: Completion

  • Sep 21

    Block A Lobby (Ground Floor) - Stage: Completion

  • Sep 21

    Cocoon Waiting Lounge - Stage: Completion

  • Sep 21

    Podium (Level 5) - Stage: Completion

  • Sep 21

    Podium (Level 5) - Stage: Completion

  • Jun 21

    Front Elevation, Block A & B

  • Jun 21

    Rear Elevation, Block A & B

  • Jun 21

    Ground Floor – Open Lawn

  • Jun 21

    Level 5 Podium

  • Mar 21

    Front Elevation, Block A & B

  • Mar 21

    Rear Elevation, Block A & B

  • Mar 21

    Block: Level 5 Podium - Stage: Landscape works in progress

  • Mar 21

    Block: Ground Floor – Open Lawn - Stage: Landscape works in progress

  • Mar 21

    Ground Floor - Futsal Court

  • Dec 20

    Front Elevation, Block A & B

  • Dec 20

    Left Elevation, Block A & B

  • Dec 20

    Right Elevation, Block A & B

  • Dec 20

    Rear Elevation, Block A & B

  • Dec 20

    Block A: Dining & Kitchen Area for Type A at Level 7 - Stage: Cleaning work completed

  • Dec 20

    Block A: Living Area for Type A at Level 7 - Stage: Cleaning work completed

  • Dec 20

    Block: Ground Floor - Road & Drainage - Stage: Landscape works in progress

  • Dec 20

    Block: Ground Floor - Road & Drainage - Stage: Landscape works in progress

  • Dec 20

    Block: Level 5 Podium - Stage: Landscape works in progress

  • Dec 20

    Security Guard House

  • Sep 20

    Block A, Block B & Podium Block

  • Sep 20

    Block A - Stage: The Structural Framework of the Said Parcel – Level 36 Units – Completed

  • Sep 20

    Block B - Stage: The Structural Framework of the Said Parcel – Level 36 Units – Completed

  • Sep 20

    Podium Block - Stage: The Structural Framework of Car Park – Podium Level – In Progress

  • Jun 20

    Block A & Block B & Podium Block - Stage: The Structural Framework of the Said Parcel – In Progress

  • Jun 20

    Block A & Block B - Stage: The Sewerage Works, Drains & Roads Serving the Said Building – In Progress

  • Jun 20

    Podium Block - Stage: The Structural Framework of Car Park – Podium Level – In Progress

  • Jun 20

    Block A - Stage: The Structural Framework of the Said Parcel – Level 36 Units – Completed

  • Jun 20

    Block B - Stage: The Structural Framework of the Said Parcel – Level 36 Units – Completed

  • Mar 20

    Block A & Block B & Podium Block - Stage: The Structural Framework of the Said Parcel – In Progress

  • Mar 20

    Block A - Stage: The Structural Framework of the Said Parcel - Level 36 Units - Completed

  • Mar 20

    Block B - Stage: The Structural Framework of the Said Parcel – Level 36 Units – Completed

  • Mar 20

    Podium Block - Stage: The Structural Framework of Car Park – Podium Level – In Progress

  • Mar 20

    Block A & Block B - Stage: The Sewerage Works, Drains & Roads Serving the Said Building – In Progress

  • Dec 19

    Block A & Block B & Podium Block - Stage: The Structural Framework of the Said Parcel – In Progress

  • Dec 19

    Block A - Stage: The Structural Framework of the Said Parcel – Level 36 Units – Completed

  • Dec 19

    Block B - Stage: The Structural Framework of the Said Parcel – Level 36 Units – Completed

  • Dec 19

    Podium Block - Stage: The Structural Framework of Car Park – Podium Level – In Progress

  • Dec 19

    Block A & Block B - Stage: The Sewerage Works, Drains & Roads Serving the Said Building – In Progress

  • Sep 19

    Block A & Block B & Podium Block - Stage : The Structural Framework of the Said Parcel – In Progress

  • Sep 19

    Podium Block - Stage: The Structural Framework of Car Park – Podium Level – In Progress

  • Sep 19

    Block A - Stage: The Ceiling, Electrical Wiring, Plumbing (without fittings), and Internal Telecommunication Trunking and Cabling to the Said Parcel– Level 20 – In Progress

  • Sep 19

    Block A - Stage: The Structural Framework of the Said Parcel – Level 36 – Completed

  • Sep 19

    Block B - Stage: The Walls of the Said Parcel with Door and Window Subframes Installed – Level 33 – In Progress

  • Sep 19

    Block B - Stage: The Structural Framework of the Said Parcel – Level 36 – Completed

  • Jun 19

    Block A & Block B & Podium Block - Stage: The Structural Framework of the Said Parcel – In Progress

  • Jun 19

    Podium Block - Stage: The Structural Framework of Car Park – Car Park Level 1A – In Progress

  • Jun 19

    Block A - Stage: The Structural Framework of the Said Parcel – Level 34 – In Progress

  • Jun 19

    Block A - Stage: The Walls of the Said Parcel with Door and Window Subframes Installed – Level 29 – In Progress

  • Jun 19

    Block A - Stage: The Ceiling, Electrical Wiring, Plumbing (without fittings), and Internal Telecommunication Trunking and Cabling to the Said Parcel– Level 15 – In Progress

  • Jun 19

    Block B - Stage: The Structural Framework of the Said Parcel – Level 29 – In Progress

  • Mar 19

    Block A & Block B & Podium Block - Stage: The Structural Framework of the Said Parcel – In Progress.

  • Mar 19

    Podium Block - Stage: The Structural Framework of Car Park – Car Park Level 1A – In Progress.

  • Mar 19

    Block A - Stage: The Structural Framework of the Said Parcel – Level 23 Units – In Progress.

  • Mar 19

    Block B - Stage: The Structural Framework of the Said Parcel – Level 16 Units – In Progress.

  • Dec 18

    Block A, Block B & Podium Block - Stage: The Structural Framework of the Said Parcel – In Progress

  • Dec 18

    Block A, Level 10 - Stage: The Structural Framework of the Said Parcel – In Progress

  • Dec 18

    Block A, Level 6 - Stage: The Walls of the Said Parcel with Door and Window Subframes installed – In Progress

  • Dec 18

    Block A, Level 6 - Stage: The Ceiling Framings, Electrical Wiring, Plumbing, Internal Telephone Trunking and Cabling – In Progress

  • Dec 18

    Block B, Level 6 - Stage: The Structural Framework of the Said Parcel – In Progress

  • Dec 18

    Podium Block, Car Park Lower Ground - Stage: The Structural Framework of Car Park – In Progress

  • Sep 18

    Block A & Block B - Stage: The Structural Framework of the Said Parcel – In Progress

  • Sep 18

    Block A - Stage: The Structural Framework of the said Parcel – Level 5 – In Progress

  • Sep 18

    Block B - Stage: The Structural Framework of the said Parcel – Car Park Transfer Level – In Progress

  • Sep 18

    Podium Block - Stage: The Structural Framework of Car Park – Car Park Lower Ground – In Progress

  • Jul 18

    Block A & B - Stage: The Structural Framework of the Said Parcel – In Progress

  • Jul 18

    Block A, Car Park Level 4 - Stage: The Structural Framework of the said Parcel – In Progress

  • Jul 18

    Block B, Car Park Level 4 - Stage: The Structural Framework of the said Parcel – In Progress

  • Jul 18

    Podium Block, Car Park Lower Ground - Stage: The Structural Framework of the said Parcel – In Progress

  • Apr 18

    Block A & B, Car Park Level 1 - Stage: The Structural Framework of the Said Parcel - In progress

  • Apr 18

    Block A, Car Park Level 1 - Stage: The Structural Framework of the Said Parcel - In progress

  • Apr 18

    Block B, Car Park Level 1 - Stage: The Structural Framework of the Said Parcel - In progress

  • Apr 18

    Podium Block, Car Park Lower Ground - Stage: The Structural Framework of the Said Parcel - In progress

  • Jan 18

    Block A & B - Aerial View

  • Jan 18

    Block A & B - Stage 2(a): Foundation Works completed

Copyright © 2023 Riana Dutamas by IJM Land Bhd & FCW Holdings Bhd
368 Segambut Sdn Bhd 201301032770 (1062599-A)
A Joint Development By